Estimating and Costing 1. __________ is prepared on the basis of plinth area of building, the rate being deducted from the cost of similar building having similar specification, heights and construction, in the locality. Supplementary Estimate Plinth Area Estimate Maintenance Estimate Cube Rate Estimate None 2. The rate of an item of work depends on Specifications of works All the above Specifications of materials Proportion of mortar None Comment 3. The brickwork is measured in sq meter, in case of Honey comb brick work Brick flat soling Half brick walls or the partition all of the above None 4. The volume is measured correct to the nearest 0.03 cum 0.04 cum 0.01 cum 0.02 cum None 5. The most reliable estimate is Detailed estimate Plinth area estimate Preliminary estimate Cubical content estimate None 6. ________________is the amount provided in the estimate and bill of quantities for some specialised work to be done by a specialised firm; whose details are not known at the time of preparing estimate. Provisional sum Prime cost Capital cost Building cost index None 7. The brick work is not measured in cu m in case of Brick work in arches Half brick wall One or more than one brick wall Reinforced brick work None 8. Pick up the item of work not included in the plinth area estimate Room area Courtyard area W.C. area Wall thickness None 9. The area is measured correct to the nearest 0.01 sq.m 0.03 sq.m 0.04 sq.m 0.02 sq.m None 10. Pick up the correct statement from the following: The gully trap disconnects the sullage drain from the main drainage system In a gully trap, a water seal of 6 to 7.5 cm is provided The gully trap collects waste water from the kitchen, sink, wash basins, etc. The grating provided over gully traps is 23 cm square None Comment 11. The measurement is not made in square metres in case of D.P.C. (Damp proof course) Form works R.C. Chhajja Concrete Jeffries None 12. According to ISI method of measurement, the order of the sequence is Breadth, length, height Height, length, breadth Length, breadth, height None of these. None 13. The main factor to be considered while preparing a detailed estimate is Transportation of materials All the above Quantity of the materials Availability of materials None 14. Pick up the correct statement from the following: The estimated value of the work excluding the amount for contingencies, work charged establishment, tool and plants, is called work value The formal acceptance by the administrative department for incurring an expenditure on the work, is called administrative approval All the above The actual expenditure involved to complete a work including incidental, establishment and travelling charges, is called actual cost None 15. _______________ estimate is a detailed estimate and is prepared to maintain the structure or work in proper order and safe condition. Maintenance estimate Revised estimate Item rate estimate Supplementary and revised estimate None 16. While estimating a reinforced cement structure, the omitted cover of concrete is assumed For reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more At the end of reinforcing bar, not less than 25 mm or twice the diameter of the bar In thin slabs, 12 mm minimum or diameter of the bar whichever is more All the above None Comment 17. To make out an estimate for a work the following data are necessary-Drawing, Specification and ___________ materials Transportation labours rates None 18. The damp proof course (D.P.C.) is measured in meters sq.m None of these cub.m None 19. The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30cm, is termed as Excavation Cutting Surface dressing Surface excavation None 20. In this method approx. total length of walls is found in running metre and this total length multiplied by the rate per running metre of wall gives a fairly accurate cost. Annual repair Cubical content estimate Item rate estimate Approximate quantity method estimate None 21. The plinth area of a building not includes Lift and wall including landing Area of cantilevered porch Area of the walls at the floor level Internal shaft for sanitary installations up to 2 sq m. in area None Comment 22. Pick up the incorrect statement from the following Areas are measured to the nearest 0.01 sq.m Weights are measured to the nearest 0.001 tonnes Dimensions are measured to the nearest 0.01 m Cubic contents are measured to the nearest 0.1 cm m None 23. The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended 175 mm 100 mm 150 mm 200 mm None 24. Pick up the incorrect statement from the following The unit of lead is 1 km where the lead exceeds 2 km Lead is the average horizontal straight distance between the borrow pit and the place of spreading soil The lead is calculated for each block of the excavated area The unit of lead is 50 m for a distance upto 500 m None 25. A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 mof the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end,and side slopes 2:1, the earth work involved. 27000 m3 27500 m3 26500 m3 26000 m3 None Comment 1 out of 5 Feel free to shareWhatsAppTwitterTelegramFacebookLinkedInPinterest